Installation and construction of lawn guardrail
1. General regulations for lawn guardrails
1. The installation of lawn guardrails should generally begin after the completion of road construction.
2. Detailed construction organization design of lawn guardrail should be made before construction and installation.
3. Make all preparations before construction. Such as: confirmation of lawn guardrail categories; preparation of various materials (wire ropes, columns, brackets, cable end anchors); various construction tools (wire rope cutters, tensioning equipment, anchoring tools, pile drivers, measuring tools, pliers) , Hammers, wrenches, spades, picks, etc.).
Second, the setting out of the lawn fence
1. The control points should be determined on the sections where lawn guardrails are installed, such as bridges, culverts, passages, openings in central dividers, three-dimensional intersections, and intersections, etc., and then measure the distance between the control points.
2. The positions of the end column, middle end column, and middle column are adjusted and positioned according to the measured distance and the distribution of control points.
3. After the position of the lawn guardrail post is determined, the location of the underground pipelines and structures should be understood in detail in order to carry out reasonable treatment.
Tel: 86-318-2052226
Phone No: +86-19933186264 (whatsapp,wechat)
Email: hgmt-web@fence-mesh.com
Add: No.21 Weier Road High and New Tech Development Zone Anping County
Main products:V Mesh Fence, Security Fence,Temporary Fence,Steel Fence, Chain Link Fence
All rights reserved©HEBEI GIANT METAL TECHNOLOGY CO.,LTD. ICP:10020944-6
Statement: part of the content of this site is from the Internet, if there is infringement, please contact the administrator to delete it as soon as possible, thank you!
Main products:V Mesh Fence, Security Fence,Temporary Fence,Steel Fence, Chain Link Fence